The stormwater improvements at McMurray Fields will help improve water quality in Como Lake by reducing the amount of stormwater flowing to the lake that carries pollutants like phosphorus. The anticipated annual pollution reductions are around 85 pounds of phosphorus, 11 tons of sediment, and an 85% reduction in stormwater flow. This project is also anticipated to reduce potable water demand for irrigation by 96%.
Practices like these stormwater improvements increase climate resiliency and reduce local flooding. Storing and reusing stormwater helps address climate trends in Minnesota, with wetter periods interspersed with extended drought.
October 27, 2026:
Current construction is focused on adding rock to the underground infiltration system, which will create space to hold water while it soaks into the ground. Excavation of the large underground storage system continues. Construction crews will be moving about 175 dump trucks worth of soil to make room for the storage system!
In the next few weeks, storm pipes will be added, sanitary sewer will be reconfigured, and installation of the underground storage system components will begin. Road closures and detour routes are expected to remain in place through the end of November.
Past Updates
October 14, 2026: Construction continues at McMurray Field. Wynne Avenue remains closed, please follow the detour route shown in earlier updates. For your safety, it is important to follow all posted signage including Sidewalk Closed signs—there is heavy machinery moving throughout the project site.
Over the next few weeks, crews will install stormwater pipes, install components of the underground infiltration system, and begin excavation of the underground storage system.
View the new signage to learn more about how McMurray Fields will help protect Como Lake!
September 29, 2026: Construction has begun at McMurray Fields! Work is currently focused on grading and excavating the area that will house the new fields and underground infiltration system.
Wynne Avenue and Beulah Lane will be closed to through traffic beginning October 5 through approximately November 20. Parking lots and local businesses will still be accessible but there will be no outlet to Lexington Parkway from Beulah Lane and Wynne Avenue. Traffic will be detoured via Jessamine Avenue.
Trails will also be closed intermittently when needed. Please follow all posted signage.
Additional updates will be provided as they become available.
September 18, 2026: Construction is planned to begin the week of September 21, and is scheduled to continue through summer 2027.
Beginning in October, a portion of Wynne Avenue will be temporarily closed, and traffic will be detoured via Jessamine Ave. During the temporary closure, Jessamine Avenue West will remain open one-way, but there will be no outlet to Lexington Parkway via Beulah Lane. There will also be temporary trail closures. More detailed road and trail closure information will be provided when available.